Fv. 5246 Slettebrekka-Hetlevik

We are building the 580-meter Hetlevik tunnel from a single portal, carrying out the breakthrough into the village under challenging conditions close to houses and existing infrastructure.

Basic information

  • Client: Vestland Fylkeskommune
  • Main contractor: Metrostav Norge AS
  • Construction time period: 06/2025 – 06/2026
  • Price: 86.000.000 NOK excluding VAT

Project characteristics

The project consists of design and construction of a new road, roundabouts and a tunnel between the villages of Slettebrekka and Hetlevik on the island of Askøy near Bergen.

The road will be approximately 2,5 km long, of which 580 meters will be in a new tunnel. There will also be 2 roundabouts, one in Haugadalen and the other one in Hetlevik. The road will relieve the existing coastal road and increase safety for all road users.

Metrostav Norge AS is excavating the 580 meter long Hetlevik tunnel. It will be excavated from only one portal and the breakthrough to village of Hetlevik must be performed without reinforcing of the portal from the outside. This will therefore be a very specific type of breakthrough close to houses and existing infrastructure.

Project data

1 pcs, total 580 m
Tunnels:
T9,5, ca 70 m2
Tunnel profile:
41 500 m3
Blasting in tunnels:
1 650 m3
Sprayed concrete:
5 100 pcs
Bolts:

Challenges / Specifics of the project

  • Design & Build project
  • Complicated breakthrough in the proximity of houses and other existing infrastructure