- Client: Statens Vegvesen
- Main contractor: Metrostav Norge AS
- Construction time period: 04/2025 – 11/2030
- Price: 2 800 000 000 NOK excluding VAT
E134 Røldal-Seljestad
Basic information
Project characteristics
The E134 Røldal-Seljestad section is the first phase of the E134 Vågsli-Seljestad project in the Ullensvang municipality. It involves the design and construction of a new road between Røldal and Seljestad. The main part of the project is the excavation of the 12.4 km long Røldal tunnel, which will replace the original 4.6 km long tunnel from the 1960s. The project also includes smaller concrete structures, 2.9 km of roads in front of and behind the tunnel and a 0.7 km long path for pedestrians and cyclists.
Metrostav Norge AS excavates the 12 400 meter long single tube Røldal tunnel from the two portals Liamyrane and Seljestad. Once excavated, the tunnel will be the 3rd longest road tunnel in Norway. The tunnel will contribute to a better and safer connection between the east and west of Norway.
Project data
Challenges / Specifics of the project
- Design & Build project
- Location of the construction site in the mountains with high snowfall
- Handling of the masses, limited depony capacities in relation to excavated amount of rock
- Electrical machinery, including loaders, excavators and trucks