Fv. 5878 Nye Nerlandsøybrua

The Fv. 5878 Nye Nerlandsøybrua project involves the construction of a 574m reinforced concrete bridge between Nerlandsøya and Bergsøya, founded on drilled piles.

Basic information

  • Main client: Møre og Romsdal Fylkeskommune
  • Contractor: Partnership Metrostav Norge AS and Bertelsen&Garpestad AS
  • Construction period: 11/2022 – 03/2025
  • Price: 442 277 896 NOK excluding VAT

Project characteristics

The Fv. 5878 Nye Nerlandsøybrua project includes the construction of a new bridge between the isles of Nerlandsøya and Bergsøya, located southwest of Ålesund.

The bridge is a reinforced concrete structure with a total length of 574 m and width of 11,5 m, divided into 8 spans, with the main span being 140 m long. The main part of the bridge will be built using the free cantilever method, and the other parts using a movable scaffolding system.

The project also includes the construction of sea embankments and the laying of the bridge foundation using large diameter bored piles.

The present bridge, constructed in 1968, will be demolished after the completion of the new one. This, however, is a part of a separate contract.

Project data

574 m, width 11,5 m
Bridge:
80 m + 140 m + 80 m
Main bridge spans:
10 962 m3
Concrete structures:
1 920 t
Reinforcement:
52 200 mMN
Prestressed reinforcement:
816 m
Large diameter piles:
14 000 m2
Asphalt:

Challenges / Specifics of the project

  • Difficult weather conditions for construction work, wind-exposed area
  • Use of a special type of foundation in the sea
  • Sea embankments
  • A remote location and complex logistics